Reporting period: September 1–30, 2025

Construction progress
Circle IV

In September, finishing and installation works were intensified. Key tasks included:

  • Installation of electrical and sanitary systems, as well as general and emergency lighting.
  • Expansion of ventilation, heating, and low-voltage systems.
  • Plastering and wall smoothing works on levels +1 to +4
  • Flooring works – screeds and installation of technical floor coverings.
  • Installation of substructures and infills of the ventilated and glass façade.

Challenges and difficulties

With the project entering final stages, material delivery schedules and on-time handovers were critical. High technical complexity required close coordination between trades.

Plans for the upcoming period

  • Commissioning of ventilation, heating, and BMS systems.
  • Installation of sanitary fittings and furniture in support areas.
  • Final touches in the stage and multifunctional hall zones.
  • Completion of façade and outdoor finishing works.

Summary

By the end of September, the construction of the IV Circle reached its final phase. The building is taking its final shape, with efforts focused on systems commissioning and preparing spaces for occupancy.

COMMENTS

Your email address will not be published. Required fields are marked *

Newsletter

Want to stay up to date? Sign up for the newsletter.

Opera Nova Functional Extension
through the expansion of the IV circle

beneficiary name

Opera Nova in Bydgoszcz

program

European Funds for Infrastructure, Climate, Environment 2021-2027

project value

144 325 394,33 PLN

action

7.1. Cultural and cultural tourism infrastructure

fund

European Regional Development Fund

EU funding

24 183 597,87 PLN

Voivodeship / County

Kuyavian-Pomeranian Voivodeship / Bydgoszcz

fund

European Regional Development Fund