Construction progress
Circle IV
In October 2025, finishing works and commissioning of internal systems continued. The key tasks included:
- Installation of ventilation, heating, and cooling systems.
- Installation of sanitary systems and technical room equipment.
- Installation of lighting fixtures, sockets, and BMS devices.
- Installation of fire alarm systems (FAS), ventilation, and emergency power supply.
- Finishing works in public and backstage areas.
- Continued site development – pavement construction.
Challenges and difficulties
The main challenge in October was the coordination of system commissioning and simultaneous finishing works in multiple areas. Precise scheduling of deliveries and installations in accordance with technological sequencing was essential.
Plans for the upcoming period
- Completion of external joinery and remaining façade elements.
- Progress in technical equipment installation: chillers, air handling units, distribution panels.
- Continued painting, flooring, and installation of interior equipment and furnishings.
- Finalization of paving works and start of permanent landscaping arrangements.
Summary
October was a month of intensive installation and finishing works. The façade of the IV Circle building is nearing closure. The facility is gradually approaching readiness for furnishing and industry-specific inspections.