Reporting period: March 1–31, 2026

Construction progress
Circle IV

In March 2026, intensive installation, façade, and finishing works continued within the 4th Circle. The scope of completed works included:

  • Installation of electrical and low-current systems across multiple floors.
  • Installation of the central heating system with radiator placement.
  • Execution of anhydrite screeds on levels +2, +2.5 and +3.
  • Plastering and finishing works in technical areas.
  • Façade assembly and sealing of façade joints.
  • Continuation of demolition works in selected areas.

Challenges and difficulties

The main challenge was coordinating multiple installation and finishing trades across several building levels while maintaining façade works continuity.

Plans for the upcoming period

  • Continuation of HVAC, electrical and low-current installations.
  • Further screed and finishing works.
  • Progress of façade works.
  • Preparation for system commissioning.

Summary

March was a period of intensive installation and finishing works. The building is approaching the final stages of construction.

COMMENTS

Your email address will not be published. Required fields are marked *

Newsletter

Want to stay up to date? Sign up for the newsletter.

Opera Nova Functional Extension
through the expansion of the IV circle

beneficiary name

Opera Nova in Bydgoszcz

program

European Funds for Infrastructure, Climate, Environment 2021-2027

project value

144 325 394,33 PLN

action

7.1. Cultural and cultural tourism infrastructure

fund

European Regional Development Fund

EU funding

24 183 597,87 PLN

Voivodeship / County

Kuyavian-Pomeranian Voivodeship / Bydgoszcz

fund

European Regional Development Fund