Reporting period: January 2025

Construction progress
Circle IV

  • Continued assembly of steel structures at level +2.5, including assembly of guy lines and steel labels.
  • Leveling of the fan room walls in preparation for the next stages of work.
  • Construction of a section of the pedestrian and bicycle path.
  • Formwork of the ceiling at level +2.5, preparing the structure for the next stages of construction.
  • Completion of work related to the construction of the ceiling at level +2.5.

Challenges and difficulties

Despite low temperatures and weather fluctuations, work is progressing according to schedule. Stable conditions have enabled the implementation of key stages of construction, both in terms of construction and finishing works.

Plans for FEBRUARY 2025

  • Further work on the pedestrian and bicycle path.
  • Continuation of leveling on level -3.
  • Start of construction of reinforced concrete structure elements on level +3.
  • Construction of intake walls on level -1.
  • Installation of ventilation ducts on levels -3 and -1.
  • Plastering work on level -2.

Summary

Despite difficult weather conditions, construction work is proceeding according to plan and there have been no significant delays. In the coming weeks, the main emphasis will be placed on continuing finishing and installation work.

COMMENTS

Your email address will not be published. Required fields are marked *

Newsletter

Want to stay up to date? Sign up for the newsletter.

Opera Nova Functional Extension
through the expansion of the IV circle

beneficiary name

Opera Nova in Bydgoszcz

program

European Funds for Infrastructure, Climate, Environment 2021-2027

project value

144 325 394,33 PLN

action

7.1. Cultural and cultural tourism infrastructure

fund

European Regional Development Fund

EU funding

24 183 597,87 PLN

Voivodeship / County

Kuyavian-Pomeranian Voivodeship / Bydgoszcz

fund

European Regional Development Fund

Scroll to top
A A+ A++ Wysoki kontrast Odwróc kolory