Construction progress
Circle IV
- Continued assembly of steel structures at level +2.5, including assembly of guy lines and steel labels.
- Leveling of the fan room walls in preparation for the next stages of work.
- Construction of a section of the pedestrian and bicycle path.
- Formwork of the ceiling at level +2.5, preparing the structure for the next stages of construction.
- Completion of work related to the construction of the ceiling at level +2.5.
Challenges and difficulties
Despite low temperatures and weather fluctuations, work is progressing according to schedule. Stable conditions have enabled the implementation of key stages of construction, both in terms of construction and finishing works.
Plans for FEBRUARY 2025
- Further work on the pedestrian and bicycle path.
- Continuation of leveling on level -3.
- Start of construction of reinforced concrete structure elements on level +3.
- Construction of intake walls on level -1.
- Installation of ventilation ducts on levels -3 and -1.
- Plastering work on level -2.
Summary
Despite difficult weather conditions, construction work is proceeding according to plan and there have been no significant delays. In the coming weeks, the main emphasis will be placed on continuing finishing and installation work.