Reporting period: December 1–31, 2025

Construction progress
Circle IV

In December 2025, intensive installation and finishing works were continued. Key completed tasks include:

  • Installation of electrical and teletechnical systems on levels -3, -2, -1, 0, +1, and +2.
  • Ongoing installation of ventilation ducts and air conditioning systems.
  • Plastering and painting of staircases F and G and backstage rooms.
  • Cement flooring works on levels from -3 to +2.
  • Installation and glazing of aluminum façade components.
  • Dismantling of the temporary roof structure over the foyer.
  • Continued work in technical and stage areas.

Challenges and difficulties

Low temperatures in the final weeks of the year and the need for concurrent execution of multiple tasks required precise scheduling and thermal protections.

Plans for the upcoming period

  • Finalizing the installation of HVAC and SSP systems.
  • Installing BMS equipment and stage infrastructure.
  • Continuing plastering, finishing, and flooring works.
  • Starting up and testing installation systems.

Summary

December marked the conclusion of a year of intense progress. The 4th Circle is now taking its final technical and spatial shape, preparing for inspections and system trials

COMMENTS

Your email address will not be published. Required fields are marked *

Newsletter

Want to stay up to date? Sign up for the newsletter.

Opera Nova Functional Extension
through the expansion of the IV circle

beneficiary name

Opera Nova in Bydgoszcz

program

European Funds for Infrastructure, Climate, Environment 2021-2027

project value

144 325 394,33 PLN

action

7.1. Cultural and cultural tourism infrastructure

fund

European Regional Development Fund

EU funding

24 183 597,87 PLN

Voivodeship / County

Kuyavian-Pomeranian Voivodeship / Bydgoszcz

fund

European Regional Development Fund

Scroll to top
A A+ A++ Wysoki kontrast Odwróc kolory