Open post

Reporting period: December 1–31, 2025

Construction progressCircle IV In December 2025, intensive installation and finishing works were continued. Key completed tasks include: Challenges and difficulties Low temperatures in the final weeks of the year and the need for concurrent execution of multiple tasks required precise scheduling and thermal protections. Plans for the upcoming period Summary December marked the conclusion of...

"Reporting period: December 1–31, 2025"Czytaj więcej

Open post

Reporting period: November 1–30, 2025

Construction progressCircle IV In November 2025, simultaneous finishing, installation, and façade works were carried out, including: Challenges and difficulties The main challenge was the coordination of works across several floors and disciplines (ventilation, air conditioning, electrical, and finishing) alongside façade and roof safety installations. Low temperatures at the end of the month required rescheduling some...

"Reporting period: November 1–30, 2025"Czytaj więcej

Open post

Reporting period: October 1–31, 2025

Construction progressCircle IV In October 2025, finishing works and commissioning of internal systems continued. The key tasks included: Challenges and difficulties The main challenge in October was the coordination of system commissioning and simultaneous finishing works in multiple areas. Precise scheduling of deliveries and installations in accordance with technological sequencing was essential. Plans for the...

"Reporting period: October 1–31, 2025"Czytaj więcej

Open post

Reporting period: September 1–30, 2025

Construction progressCircle IV In September, finishing and installation works were intensified. Key tasks included: Challenges and difficulties With the project entering final stages, material delivery schedules and on-time handovers were critical. High technical complexity required close coordination between trades. Plans for the upcoming period Summary By the end of September, the construction of the IV...

"Reporting period: September 1–30, 2025"Czytaj więcej

Open post

Reporting period: August 1–31, 2025

Construction progressCircle IV In August 2025, construction works focused on intensifying interior finishing, continuing façade installations, and progressing with technical systems. The following tasks were completed: Challenges and difficulties The greatest challenge was coordinating simultaneous finishing and technical installations across multiple floors. This required flexible scheduling and continuous site supervision. Plans for the upcoming period...

"Reporting period: August 1–31, 2025"Czytaj więcej

Open post

Reporting period: July 1–31, 2025

Construction progressCircle IV In July 2025, advanced finishing and installation works were continued throughout the building, along with façade installation and site development. The following tasks were completed: Challenges and difficulties Despite favorable weather conditions, coordinating multiple trades working simultaneously in different building areas remained a challenge. Particular attention was paid to the quality control...

"Reporting period: July 1–31, 2025"Czytaj więcej

Open post

Reporting period: June 1–30, 2025

Construction progressCircle IV In June 2025, the project focused on closing the building shell, continuing finishing and installation works, and progressing with external works. The following tasks were completed: Challenges and difficulties June was characterized by stable weather conducive to accelerating outdoor works. The main challenge was coordinating multiple simultaneous tasks performed by different contractor...

"Reporting period: June 1–30, 2025"Czytaj więcej

Open post

Reporting period: May 1–31, 2025

Construction progressCircle IV In May 2025, construction activities focused on completing the reinforced concrete structure of the building and intensifying masonry and installation works. The following tasks were completed: Challenges and difficulties May featured favorable weather for structural work. However, the simultaneous execution of works by multiple trades on different levels of the building posed...

"Reporting period: May 1–31, 2025"Czytaj więcej

Open post

Reporting period: April 1–30, 2025

Construction progressCircle IV In April 2025, work continued mainly on reinforced concrete structures and preparations for installations and masonry. The completed activities included: Challenges and difficulties In April, works were carried out under variable weather conditions, including periodic precipitation and temperature drops, especially in the first ten days of the month. Nevertheless, thanks to proper...

"Reporting period: April 1–30, 2025"Czytaj więcej

Open post

Reporting period: 1 – 31 March 2025

Construction progressCircle IV In March 2025, work on the construction of the IV Circle of Opera Nova focused on the continuation of structural works and preparations for the next finishing stages. The main completed tasks included: Challenges and difficulties During the execution of construction work, challenges were encountered due to unfavorable weather conditions—particularly low temperatures...

"Reporting period: 1 – 31 March 2025"Czytaj więcej

Newsletter

Want to stay up to date? Sign up for the newsletter.

Opera Nova Functional Extension
through the expansion of the IV circle

beneficiary name

Opera Nova in Bydgoszcz

program

European Funds for Infrastructure, Climate, Environment 2021-2027

project value

144 325 394,33 PLN

action

7.1. Cultural and cultural tourism infrastructure

fund

European Regional Development Fund

EU funding

24 183 597,87 PLN

Voivodeship / County

Kuyavian-Pomeranian Voivodeship / Bydgoszcz

fund

European Regional Development Fund

Scroll to top
A A+ A++ Wysoki kontrast Odwróc kolory