Open post

Reporting period: July 1–31, 2026

Construction progressCircle IV In July 2026, intensive finishing, installation and façade works continued within the 4th Circle. The main works carried out during the reporting period included: Challenges and difficulties A key organisational challenge remained the coordination of multiple trades working simultaneously, particularly in areas where technical installations, wall and floor finishes, suspended ceilings and...

"Reporting period: July 1–31, 2026"Czytaj więcej

Open post

Reporting period: June 1–30, 2026

Construction progressCircle IV During June 2026, intensive finishing, installation and façade works continued within the 4th Circle. The main completed activities included: Challenges and difficulties The main challenge during the reporting period was coordinating numerous finishing, installation and façade activities carried out simultaneously across multiple building areas. Maintaining continuity of façade installation while preparing additional...

"Reporting period: June 1–30, 2026"Czytaj więcej

Open post

Reporting period: MAY 1–31, 2026

Construction progressCircle IV In May 2026, intensive installation, façade and finishing works continued within the 4th Circle. The scope of completed works included: Challenges and difficulties The main challenge was coordinating numerous installation, façade and finishing works carried out simultaneously in multiple areas of the building. An important organizational task was also aligning the work...

"Reporting period: MAY 1–31, 2026"Czytaj więcej

Open post

Reporting period: April 1–30, 2026

Construction progressCircle IV In April 2026, intensive installation, façade, and finishing works continued within the 4th Circle. The scope of completed works included: Challenges and difficulties The main challenge was coordinating simultaneous installation, finishing, and façade works carried out across multiple floors of the building. Additionally, work schedules had to be adapted to the sequencing...

"Reporting period: April 1–30, 2026"Czytaj więcej

Open post

Reporting period: Q1 2026

Construction progressCircle IV In the first quarter of 2026, intensive installation, façade, and finishing works continued within the 4th Circle. Works were carried out simultaneously across multiple levels of the building. The key completed works included: Challenges and difficulties The main challenge during the quarter was coordinating multiple installation and finishing trades working simultaneously across...

"Reporting period: Q1 2026"Czytaj więcej

Open post

Reporting period: March 1–31, 2026

Construction progressCircle IV In March 2026, intensive installation, façade, and finishing works continued within the 4th Circle. The scope of completed works included: Challenges and difficulties The main challenge was coordinating multiple installation and finishing trades across several building levels while maintaining façade works continuity. Plans for the upcoming period Summary March was a period...

"Reporting period: March 1–31, 2026"Czytaj więcej

Open post

Reporting period: February 1–28, 2026

Construction progressCircle IV In February 2026, intensive installation, façade, and finishing works continued within the 4th Circle. The scope of completed works included: Challenges and difficulties The main challenge was coordinating multiple installation trades working simultaneously on several floors of the building. Low temperatures at the beginning of the month also required additional protection of...

"Reporting period: February 1–28, 2026"Czytaj więcej

Open post

Reporting period: January 1–31, 2026

Construction progressCircle IV In January 2026, intensive installation, façade, and finishing works continued within the 4th Circle. The scope of completed works included: Challenges and difficulties January was marked by low temperatures (locally below -5°C), requiring protection of installation works and adjustments to the schedule of external activities. Additional challenges included coordinating finishing works with...

"Reporting period: January 1–31, 2026"Czytaj więcej

Open post

Reporting period: December 1–31, 2025

Construction progressCircle IV In December 2025, intensive installation and finishing works were continued. Key completed tasks include: Challenges and difficulties Low temperatures in the final weeks of the year and the need for concurrent execution of multiple tasks required precise scheduling and thermal protections. Plans for the upcoming period Summary December marked the conclusion of...

"Reporting period: December 1–31, 2025"Czytaj więcej

Open post

Reporting period: November 1–30, 2025

Construction progressCircle IV In November 2025, simultaneous finishing, installation, and façade works were carried out, including: Challenges and difficulties The main challenge was the coordination of works across several floors and disciplines (ventilation, air conditioning, electrical, and finishing) alongside façade and roof safety installations. Low temperatures at the end of the month required rescheduling some...

"Reporting period: November 1–30, 2025"Czytaj więcej

Newsletter

Want to stay up to date? Sign up for the newsletter.

Opera Nova Functional Extension
through the expansion of the IV circle

beneficiary name

Opera Nova in Bydgoszcz

program

European Funds for Infrastructure, Climate, Environment 2021-2027

project value

144 325 394,33 PLN

action

7.1. Cultural and cultural tourism infrastructure

fund

European Regional Development Fund

EU funding

24 183 597,87 PLN

Voivodeship / County

Kuyavian-Pomeranian Voivodeship / Bydgoszcz

fund

European Regional Development Fund

Scroll to top
A A+ A++ Wysoki kontrast Odwróc kolory