Construction progressCircle IV In April 2026, intensive installation, façade, and finishing works continued within the 4th Circle. The scope of completed works included: Challenges and difficulties The main challenge was coordinating simultaneous installation, finishing, and façade works carried out across multiple floors of the building. Additionally, work schedules had to be adapted to the sequencing...
"Reporting period: April 1–30, 2026"Czytaj więcej